Tender Issued for Five 10 MW/40MWh Battery Energy Storage Projects in Uttar Pradesh

The last day to submit the bids is December 24, 2022

thumbnail

Uttar Pradesh Power Corporation (UPPCL) has issued Requests for Selection (RfS) to set up five standalone Battery Energy Storage Systems (BESS) of 10 MW/40 MWh each in Uttar Pradesh.

The projects will be set up in Dasna, Hasayan, Jalesar, Boner, and Vrindavan. The projects will be set up under build, own, operate, and transfer mode for 12 years. The work must be completed within 18 months of signing the Battery Energy Storage Purchase Agreement (BESPA).

The last day to submit the bids is December 24, 2022. The bids will be opened on December 27.

The cost of the bidding documents is ₹25,000 (~$303), and the document processing fee is ₹100,000 (~$1,214). Interested bidders must submit an earnest money deposit of ₹740,000 (~$8,989)/MW of quoted capacity. Successful bidders must furnish a Performance Bank Guarantee (PBG) of ₹1.11 million (~$13,465)/MW/Project before signing the BESPA.

Before commissioning the project’s first part capacity, the developer must furnish a security deposit of ₹500,000 (~$6,065)/MWh to UPPCL.

Bidders must have a net worth of ₹11.6 million (~$140,722)/MW of quoted capacity. The minimum annual turnover of the bidders must be ₹2.9 million (~$35,180)/MW of quoted capacity. Internal resource generation capability, in the form of Profit Before Depreciation Interest and Taxes (PBDIT), must be ₹580,000 (~$7,036)/MW of quoted capacity. Bidders must furnish an in-principle sanction letter from the banks of the bidder, committing a line of credit for a minimum amount of ₹725,000(~$8,795)/ MW of quoted capacity.

The projects will be located in the vicinity of the available 132/33 kV substation of the intra-state network. Land identification and allocation will be under the scope of the transmission licensee owning the identified substation. The land will be provided on a lease or right-to-use basis to the developer. The BESS may be charged by any energy source, including conventional energy sources.

In case of delay in commissioning, the total PBG amount for the project will be encashed on a per-day basis and proportionate to the balance capacity not commissioned.

In September, The Uttar Pradesh Electricity Regulatory Commission approved the request by the UPPCL to issue a tender to install BESS projects with a capacity of 10 MW/40 MWh each in the state.

Recently, the Ministry of Power issued the Renewable Purchase Obligation trajectory until the financial year 2029-2030. The notification for the first time included energy storage obligation to be met by all state DISCOMs.

In March 2022, the Ministry issued guidelines to procure and utilize BESS as part of the generation, transmission, and distribution assets, along with ancillary services.

RELATED POSTS

Get the most relevant India solar and clean energy news.

Featured
thumbnail
14:46 Installs a Record 2.5 GW of Solar Open Access in 2022, Up 92% YoY

India added 2.5 GW of solar open access in the calendar year (CY) 2022, a year-over-year (YoY) increase of 92% from the 1.3 GW installed in CY 2021, according to the newly released 2022 Q4 & Annual Mercom India Solar Open ...

March 16, 2023

Markets & Policy

25% of Generation Capacity of Coal Plants Must be from Renewables: Ministry of Power

The Ministry of Power (MoP) has proposed that any coal-based thermal generation station coming up after April 1, 2024, must either install or procure renewable energy equivalent to 25% of the thermal generation capacity. Stakehold...

November 9, 2022

Mercom Research Focus

India’s Solar Market Leaders for 1H 2022

Mercom India has released its report, India Solar Market Leaderboard 1H 2022, unveiling solar market leaders in the first half (1H) of the calendar year (CY) 2022. The report covers market share and shipment rankings across the In...

November 9, 2022

Energy Storage

Webinar to Shed Light on How Battery Storage Enhance Solar Systems’ Performance

Battery energy storage technologies globally are transforming how companies utilize, control, and dispatch electricity and facilitating a smoother transition to clean energy. The Indian market is also realizing how battery storage...

November 9, 2022

Magazine

DON'T MISS AN ISSUE!

Mercom Cleantech Magazine

Get Your Copy Today!

magazines

Latest News

Test Video Post2

This is custom content that will be displayed at the video in case you want to give an overview, etc. Michael Ballard

November 30, 2022

thumbnail
14:46 Installs a Record 2.5 GW of Solar Open Access in 2022, Up 92% YoY

India added 2.5 GW of solar open access in the calendar year (CY) 2022, a year-over-year (YoY) increase of 92% from the 1.3 GW installed in CY 2021, according to the newly released 2022 Q4 & Annual Mercom India Solar Open...

March 16, 2023

thumbnail
25% of Generation Capacity of Coal Plants Must be from Renewables: Ministry of Power

The Ministry of Power (MoP) has proposed that any coal-based thermal generation station coming up after April 1, 2024, must either install or procure renewable energy equivalent to 25% of the thermal generation capacity....

November 9, 2022

JANUARY 2023

Some test content that can be displayed somewhere maybe if needed? Not sure Michael Ballard

November 30, 2022

DECEMBER 2022

December 2022 Magazine Post Michael Ballard

March 2, 2023

NOVEMBER 2022

March 2, 2023

Mercom India Renewables Summit 2023

OUR FLAGSHIP EVENT, MERCOM INDIA RENEWABLES SUMMIT, APRIL 2023   Mercom India Renewables Summit 2023 (formerly Mercom India Solar Summit) brings together developers, manufacturers, investors, innovators, and other key decision...

November 28, 2022

thumbnail
PTC India’s EoI to Procure 1 GW of Hybrid Power Receives Overwhelming Response

PTC India’s expression of interest (EoI) to procure 500 MW of hybrid renewable energy (wind and solar) (Tranche-I), with a greenshoe option for an additional 500 MW, has received a strong response, according to Mercom sources....

November 9, 2022

thumbnail
Higher Operating Costs Drive Fuel Cell Firm Ballard’s Net Loss Up 39% YoY in Q3

Ballard Power Systems, a fuel cell and clean energy solutions provider, recorded a net loss of $42.88 million in the third quarter (Q3) of 2022, a year-over-year (YoY) increase of 39%. The revenue for the quarter was $21.34...

November 9, 2022

thumbnail
Solid Power Posts Loss of $12.4 Million in Q3 As Operating Expenses Soar

Solid Power, Inc., a U.S.-based developer of all-solid-state battery cells for electric vehicles (EVs), reported a net loss of $12.4 million for the third quarter (Q3) 2022, a 46% increase from the $8.45 million loss during the...

November 9, 2022

MORE NEWS