CERC Yet to Act on ISTS Charges Waiver for Open Access Renewables Proposed by Ministry of Power

ISTS waiver is attractive to C&I consumers, but uncertainty is hindering capacity addition

thumbnail

Nearly a year after the Ministry of Power (MOP) extended the timeline and widened the scope for waiver of the interstate transmission system (ISTS) charges for renewable energy projects, the expected surge in the open access solar market has not materialized because the Central Electricity Regulatory Commission (CERC) has not included the provisions in relevant amendments.

This has caused uncertainty for developers leading to slow progress in some projects. An executive from an open access developer said, “Developers are in a fix. If they build their projects based on the MoP order, they could suffer if CERC decides not to incorporate them. But if projects are held back until CERC’s regulations are finalized, we might not have enough time to avail 100% ISTS waiver.”

So far, CERC has released a draft amendment to the Sharing of Inter-State Transmission Charges and Losses (First Amendment) Regulations, 2022, but it does not include the developer-friendly provisions laid out in last November’s MoP order.

In stakeholder comments, MoP wrote to CERC earlier this month, “It is observed that the proposed supplementary amendment also is not in line with the provisions regarding waiver of transmission charges as per aforesaid MoP orders.” The letter noted that the ministry had written to CERC in August as well, urging it to include the provisions of its order in the regulations.

Emphasizing the scale of uncertainty over projects, another industry source said, “Developers are building close to 1 GW of ISTS projects in Rajasthan. They have also received the connectivity for it, but the regulatory uncertainty is holding back the projects from going ahead full steam.”

The ISTS charges waiver offers significant cost benefits to open access consumers. A commercial and industrial (C&I) unit stands to save around ₹0.50 (~$0.006)/kWh in ISTS charges when procuring renewable power. For a C&I consumer with a 50 MW requirement, the ISTS charges could be over ₹70 million in a year, assuming the unit runs for 8 hours a day for 365 days.

Power Ministry’s Order on ISTS Waiver

MoP’s order last year encouraged capacity addition through ISTS open access projects by bringing in private investment. The ministry extended the commissioning date for solar and wind energy projects by two years to June 30, 2025, as an eligibility criterion to avail of ISTS charges waiver for 25 years. Further, pumped hydro storage projects and battery energy storage systems (BESS), along with solar and wind energy, were also included in the waiver.

While the earlier ISTS charges waiver was applicable only for DISCOMs procuring power through competitive bidding, the ministry’s order extended it for captive use, power exchanges, and bilateral agreements.

The ISTS charge waiver is contingent on the commissioning time and progressively reduces every year. Projects commissioned by June 30, 2025, can avail of a 100% waiver on the ISTS charges. From then on, the extent of waiver declines progressively, as illustrated in the chart below –

ISTS Charges Chart

Boost to ISTS-connected Open Access

The ISTS charges waiver allows C&I consumers another power procurement option on the table. For instance, many consumers based in Industrialized states with expensive land, like Haryana and Maharashtra, would prefer third-party solar open access from projects in Rajasthan or Gujarat. But ISTS charges make it prohibitive for them.

The current model of solar open access is almost entirely limited to captive/group captive or third-party projects developed in the same state where the C&I consumers are based.

“Currently, Delhi Metro is the only C&I consumer for inter-state open access as it buys power from the solar park in Rewa in Madhya Pradesh,” a source said. However, developers say that many consumers, especially those with large energy requirements, are looking at the ISTS open access option.

The open access arrangement saves C&I consumers from high distribution companies (DISCOM) charges, especially the cross-subsidy component. The intra-state model could be restrictive due to the scarcity of land or investment required for building captive units.

Consumer interest in ISTS open access projects is reflected in the recent announcement by Amazon, which roped in three developers for 420 MW solar projects in Rajasthan.

Industry sources said that apart from resolving the prevailing uncertainty, the state governments must reform their ISTS regulations to maximize the open access opportunity. “Very few states have open access projects. And where open access projects are present, the interstate policies are not impactful enough to make any difference to the business,” another developer added.

Large solar parks that provide power to other state DISCOMs have been the mainstay of solar capacity addition in India. The ISTS charges waiver for bilateral and captive projects aims to provide a cheaper source of renewable power for the industry, promote private investment in the sector and unlock large capacity additions.

“Nothing kills investments like uncertainty. Unfortunately, delays in decision-making fester uncertainty and bog down growth, which has become all too common in the solar industry. The industry needs decisions to be taken swiftly on pending regulations and issues to remove bottlenecks and provide confidence to investors,” said Raj Prabhu, CEO of Mercom Capital Group.

RELATED POSTS

Get the most relevant India solar and clean energy news.

Featured
thumbnail
14:46 Installs a Record 2.5 GW of Solar Open Access in 2022, Up 92% YoY

India added 2.5 GW of solar open access in the calendar year (CY) 2022, a year-over-year (YoY) increase of 92% from the 1.3 GW installed in CY 2021, according to the newly released 2022 Q4 & Annual Mercom India Solar Open ...

March 16, 2023

Markets & Policy

25% of Generation Capacity of Coal Plants Must be from Renewables: Ministry of Power

The Ministry of Power (MoP) has proposed that any coal-based thermal generation station coming up after April 1, 2024, must either install or procure renewable energy equivalent to 25% of the thermal generation capacity. Stakehold...

November 9, 2022

Mercom Research Focus

India’s Solar Market Leaders for 1H 2022

Mercom India has released its report, India Solar Market Leaderboard 1H 2022, unveiling solar market leaders in the first half (1H) of the calendar year (CY) 2022. The report covers market share and shipment rankings across the In...

November 9, 2022

Energy Storage

Webinar to Shed Light on How Battery Storage Enhance Solar Systems’ Performance

Battery energy storage technologies globally are transforming how companies utilize, control, and dispatch electricity and facilitating a smoother transition to clean energy. The Indian market is also realizing how battery storage...

November 9, 2022

Magazine

DON'T MISS AN ISSUE!

Mercom Cleantech Magazine

Get Your Copy Today!

magazines

Latest News

Test Video Post2

This is custom content that will be displayed at the video in case you want to give an overview, etc. Michael Ballard

November 30, 2022

thumbnail
14:46 Installs a Record 2.5 GW of Solar Open Access in 2022, Up 92% YoY

India added 2.5 GW of solar open access in the calendar year (CY) 2022, a year-over-year (YoY) increase of 92% from the 1.3 GW installed in CY 2021, according to the newly released 2022 Q4 & Annual Mercom India Solar Open...

March 16, 2023

thumbnail
25% of Generation Capacity of Coal Plants Must be from Renewables: Ministry of Power

The Ministry of Power (MoP) has proposed that any coal-based thermal generation station coming up after April 1, 2024, must either install or procure renewable energy equivalent to 25% of the thermal generation capacity....

November 9, 2022

JANUARY 2023

Some test content that can be displayed somewhere maybe if needed? Not sure Michael Ballard

November 30, 2022

DECEMBER 2022

December 2022 Magazine Post Michael Ballard

March 2, 2023

NOVEMBER 2022

March 2, 2023

Mercom India Renewables Summit 2023

OUR FLAGSHIP EVENT, MERCOM INDIA RENEWABLES SUMMIT, APRIL 2023   Mercom India Renewables Summit 2023 (formerly Mercom India Solar Summit) brings together developers, manufacturers, investors, innovators, and other key decision...

November 28, 2022

thumbnail
PTC India’s EoI to Procure 1 GW of Hybrid Power Receives Overwhelming Response

PTC India’s expression of interest (EoI) to procure 500 MW of hybrid renewable energy (wind and solar) (Tranche-I), with a greenshoe option for an additional 500 MW, has received a strong response, according to Mercom sources....

November 9, 2022

thumbnail
Higher Operating Costs Drive Fuel Cell Firm Ballard’s Net Loss Up 39% YoY in Q3

Ballard Power Systems, a fuel cell and clean energy solutions provider, recorded a net loss of $42.88 million in the third quarter (Q3) of 2022, a year-over-year (YoY) increase of 39%. The revenue for the quarter was $21.34...

November 9, 2022

thumbnail
Solid Power Posts Loss of $12.4 Million in Q3 As Operating Expenses Soar

Solid Power, Inc., a U.S.-based developer of all-solid-state battery cells for electric vehicles (EVs), reported a net loss of $12.4 million for the third quarter (Q3) 2022, a 46% increase from the $8.45 million loss during the...

November 9, 2022

MORE NEWS